Construction Update - #23 | | May 31, 2006 
Building A
- ceilings began May 12th
- flooring completed May 26th
- windows are almost complete, waiting for spandrel glass
- painting began May 8th
- HVAC is being completed
- light fixtures are complete
- laboratory cabinetry scheduled for end of May
- 1st floor metal studs nearly complete; roughing in electrical and mechanical
- basement all items to be completed by end of June/beginning of July
- lab scheduled to open in July
Building B - basement framing is complete
- HVAC is being completed
- sheet rock and window installation nearly complete
- taping scheduled to start this week; painting scheduled to start next week
- all items in basement completed by end of June
- cafeteria projected move-in date is July 1st
Building C - grading completed
- columns completed
- concrete wall forming has started
- floor slab scheduled for June 7th
Other notes: - the magnolia tree, replanted at Woodridge, is alive and budding
|
|
 |